Aker will supply the steel substructure for the 2GW high-voltage direct current (HVDC) converter station of the project with ...
Aker Solutions awarded contract for BalWin 1 offshore wind project. Find the latest news from the maritime industry on the PortNews website.
Aker Solutions has signed a contract with Dragados Offshore to deliver the steel substructure for the 2 GW HVDC converter ...
Aker Solutions has signed a significant1 contract with Dragados Offshore to deliver the steel substructure for the 2GW HVDC converter station for the BalWin1 offshore wind grid connection system in ...
Aker Solutions has been awarded what it described as ‘a significant contract’ to deliver the steel substructure for BalWin1 offshore substation The substation, a convertor station, is a key part of ...